Province | Subbasin | % |
---|---|---|
Columbia Plateau | Snake Lower | 100.00% |
Previous: | Next: |
---|---|
73354 REL 79: 2007-401-00 EXP KELT RECONDITIONING/REPRODUCTIVE SUCCESS 2022 |
|
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Environmental Coverage Documents | A: 165. Produce Environmental compliance document for kelt activities | 06/30/2024 | 06/27/2024 | |
Kelt Steelhead Collections | B: 66. Collect, hold, and transport kelt steelhead for experiments | 06/30/2024 | 06/27/2024 | |
Produce accessible, error-checked datasets | C: 157. Collect biological data and tissue for genotyping from adult steelhead | 06/30/2024 | 06/27/2024 | |
Order PIT tags | D: 158. PIT tag adult steelhead at collection sites | 06/30/2024 | 06/27/2024 | |
Recondition Kelt Steelhead for Release back to the River of Collection | E: 176. Recondition kelt steelhead for long term treatments | 06/30/2024 | 06/27/2024 | |
Collect biological data on reconditioned kelt steelhead | F: 157. Collect survival, condition, and rematuration data on reared kelt steelhead | 06/30/2024 | 06/27/2024 | |
Analysis long-term data | G: 162. Analyze kelt steelhead post rearing data | 06/30/2024 | 06/27/2024 | |
Generate genotype data from fish tissue samples | H: 157. Genotype tissue samples from adult and kelt steelhead, and from resident O. mykiss | 06/30/2024 | 06/27/2024 | |
Analyze genetic data | I: 162. Conduct parentage assignments, and stock identification from genetic data | 06/30/2024 | 06/27/2024 | |
Implement Snake River Kelt Plan | J: 157. Implement Snake River Kelt Reconditioning Plan | 06/30/2024 | 06/27/2024 | |
National and Regional Conference Participation | K: 161. Present findings with presentations | 06/30/2024 | 06/27/2024 | |
Work toward publication of manuscripts | L: 183. Work toward submitting a peer-reviewed journal article | 06/30/2024 | 06/27/2024 | |
Hatchery Reconditioning Plan | M: 174. Hatchery Reconditiong Plan | 06/30/2024 | 06/27/2024 | |
Project wrap up, delineation of necessary follow up monitoring and research, complete manuscripts, transition to other locations or uses of kelt reconditioning technology. | N: 174. Project Transition, wrap up of experiments and developing new lines of investigation. | 06/30/2024 | 06/27/2024 | |
Construction Management Complete | O: 100. Cultural Monitor during Construction of kelt facility at NPTH | 06/30/2024 | 06/27/2024 | |
Effective implementation management and timely contract administration | P: 119. Manage project and subcontracts for kelt project | 06/30/2024 | 06/27/2024 | |
Completed Annual Report | Q: 132. Submit 2023 Annual Report for January 2023 to December 2023 | 03/29/2024 | 03/27/2024 |
Primary Focal Species | Work Statement Elements |
---|---|
Steelhead (Oncorhynchus mykiss) - All Populations |
|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Produce Environmental compliance document for kelt activities | |||||||
B | 66 | Collect, hold, and transport kelt steelhead for experiments | 04/06/2023 | ||||||
C | 157 | Collect biological data and tissue for genotyping from adult steelhead | 04/06/2023 | ||||||
D | 158 | PIT tag adult steelhead at collection sites | 04/06/2023 | ||||||
E | 176 | Recondition kelt steelhead for long term treatments | 04/06/2023 | ||||||
F | 157 | Collect survival, condition, and rematuration data on reared kelt steelhead | 04/06/2023 | ||||||
G | 162 | Analyze kelt steelhead post rearing data | |||||||
H | 157 | Genotype tissue samples from adult and kelt steelhead, and from resident O. mykiss | 04/06/2023 | ||||||
I | 162 | Conduct parentage assignments, and stock identification from genetic data | |||||||
J | 157 | Implement Snake River Kelt Reconditioning Plan | 04/06/2023 | ||||||
K | 161 | Present findings with presentations | |||||||
L | 183 | Work toward submitting a peer-reviewed journal article | |||||||
M | 174 | Hatchery Reconditiong Plan | 04/06/2023 | ||||||
N | 174 | Project Transition, wrap up of experiments and developing new lines of investigation. | 04/06/2023 | ||||||
O | 100 | Cultural Monitor during Construction of kelt facility at NPTH | |||||||
P | 119 | Manage project and subcontracts for kelt project | |||||||
Q | 132 | Submit 2023 Annual Report for January 2023 to December 2023 | |||||||
R | 185 | Quarterly Status Reports |